Portfolio & Experience

Engineering Experience Across Renewable Energy and Industrial Systems

Explore Kuantum Enerji's company experience and founder-level project background through verified source references, field work, and energy-sector applications.

Verified Experience

Company and founder-level references

The portfolio data below is migrated from the legacy Kuantum Enerji experience page and split into the two primary categories requested for the new site.

Company Experiences

Experiences/projects directly related to Kuantum Enerji as a company.

9 verified items

Founder’s Experiences

Founder-level project background preserved from the verified legacy source.

8 verified items
Diyarbakır Solar Power Plants source image
Company Experiences Finished

Diyarbakır Solar Power Plants

DIYARBAKIR / TURKEY

PROJECT NAME
Diyarbakır Solar Power Plants
PLACE
DIYARBAKIR / TURKEY
EMPLOYER
IPP
START OF DATE
2017
FINISH OF DATE
2017

SCOPE OF WORKS

  • Annual Production (kWh/y) : 1.900.000 X 12
  • Annual Radiation (kWh/m²) : 1.885
  • Installed Capacity (kWp) : 1.192
  • Main Purpose : Energy Generation and Testing Different Types of Modules and Invertors
  • In this plant 2 type of modules and 2 type of invertors will be tested and compared with each other. Having near by place Diyarbakır, the plant will be under our observation at any time and would be served as laboratory.
Şanlıurfa Solar Power Plants source image
Company Experiences Finished

Şanlıurfa Solar Power Plants

ŞANLIURFA / TURKEY

PROJECT NAME
Şanlıurfa Solar Power Plants
PLACE
ŞANLIURFA / TURKEY
EMPLOYER
IPP
START OF DATE
2018
FINISH OF DATE
2019

SCOPE OF WORKS

  • Annual Production (kWh/y) : 950.000 X 6
  • Annual Radiation (kWh/m²) : 1.960
  • Installed Capacity (kWp) : 600
  • Main Purpose : Green and Clear Energy Generation
  • In this plant 1 type of PV module and 1 type of invertor will be installed.
Batman Solid Waste Integrated Facility and Hybrid Power Plant source image
Batman Solid Waste Integrated Facility site source image
Company Experiences Finished

BATMAN SOLID WASTE INTEGRATED FACILITY & BATMAN HYBRID POWER PLANT

BATMAN / TURKEY

PROJECT NAME
BATMAN SOLID WASTE INTEGRATED FACILITY & BATMAN HYBRID POWER PLANT
PLACE
BATMAN / TURKEY
EMPLOYER
EPC
START OF DATE
2019
FINISH OF DATE
2023

SCOPE OF WORKS

  • Rehabilitation of Wild Landfill Site
  • Biomass Power Plant — 6.24 MWe
  • Solid Waste Landfill Site
  • Solid Waste Separation Plant (Mechanical Separation Plant)
  • Hazardous Waste Landfill Site
  • Hazardous Waste Disposal Facility
  • Biogas Power Plant — 1.56 MWe
  • Biomethanization Reactor, together with TÜBİTAK — 250 kWe
  • Solar Power Plant — 6.24 MWp
  • Wind Power Plant — 500 kWe
  • Waste Derived Fuel Plant (WDF)
  • Medical Waste Sterilization Plant
  • Leachate Treatment Plant
  • Compost Facility (Organic Fertilizer Production Plant)
  • Greenhouse, agriculture and sapling production, including high-value-added and industrial products
  • R&D activities together with TÜBİTAK and the university
  • Social projects focused on creating new-generation environmental awareness
EMEKSAN Roof Solar Power Plants source image
Company Experiences Finished

EMEKSAN Roof Solar Power Plants

BATMAN / TURKEY

PROJECT NAME
EMEKSAN Roof Solar Power Plants
PLACE
BATMAN / TURKEY
EMPLOYER
EPC
START OF DATE
2022
FINISH OF DATE
2022

SCOPE OF WORKS

  • Installed Capacity (kWp): 620
  • Main Purpose: Green and Clean Energy Generation
  • One type of PV module and one type of inverter was installed.
NUREL TARIM Roof Solar Power Plants source image
Company Experiences Finished

NUREL TARIM Roof Solar Power Plants

BATMAN / TURKEY

PROJECT NAME
NUREL TARIM Roof Solar Power Plants
PLACE
BATMAN / TURKEY
EMPLOYER
EPC
START OF DATE
2022
FINISH OF DATE
2022

SCOPE OF WORKS

  • Installed Capacity (kWp): 730
  • Main Purpose: Green and Clean Energy Generation
  • One type of PV module and one type of inverter was installed.
ASLANKAYA TEKSTIL BADU Roof Solar Power Plants source image
Company Experiences Finished

ASLANKAYA TEKSTIL BADU Roof Solar Power Plants

MARDİN / TURKEY

PROJECT NAME
ASLANKAYA TEKSTIL BADU Roof Solar Power Plants
PLACE
MARDİN / TURKEY
EMPLOYER
EPC
START OF DATE
2022
FINISH OF DATE
2022

SCOPE OF WORKS

  • Installed Capacity (kWp): 782
  • Main Purpose: Green and Clean Energy Generation
  • One type of PV module and one type of inverter was installed.
Diyarbakır Solid Waste Integrated Facility source image
Diyarbakır Hybrid Power Plant source image
Company Experiences Finished

DIYARBAKIR SOLID WASTE INTEGRATED FACILITY & DIYARBAKIR HYBRID POWER PLANT

DIYARBAKIR / TURKEY

PROJECT NAME
DIYARBAKIR SOLID WASTE INTEGRATED FACILITY & DIYARBAKIR HYBRID POWER PLANT
PLACE
DIYARBAKIR / TURKEY
EMPLOYER
EPC
START OF DATE
2022
FINISH OF DATE
2024

SCOPE OF WORKS

  • Rehabilitation of Wild Landfill Site
  • Biomass Power Plant — 14.50 MWe
  • Solid Waste Landfill Site
  • Solid Waste Separation Plant (Mechanical Separation Plant)
  • Hazardous Waste Landfill Site
  • Hazardous Waste Disposal Facility
  • Solar Power Plant — 14.50 MWp
  • Waste Derived Fuel Plant (WDF)
  • Medical Waste Sterilization Plant
  • Leachate Treatment Plant
  • Compost Facility (Organic Fertilizer Production Plant)
  • Greenhouse, Agriculture and Sapling production, including high-value-added and industrial products
  • Social projects focused on creating new-generation environmental awareness
ULTRA Viranşehir Solar Power Plants source image
ULTRA Viranşehir Solar Power Plants aerial source image
Company Experiences Finished

ULTRA Viranşehir Solar Power Plants

ŞANLIURFA / TURKEY

PROJECT NAME
ULTRA Viranşehir Solar Power Plants
PLACE
ŞANLIURFA / TURKEY
EMPLOYER
EPC
START OF DATE
2023
FINISH OF DATE
2024

SCOPE OF WORKS

  • Annual Production (kWh/year): 1,900,000 × 7.2
  • Annual Radiation (kWh/m²): 1,885
  • Installed Capacity (kWp): 7,200
  • Ultra EMAR, a company belonging to Ultra Hospitals, has completed the installation of its self-consumption solar power plant.
  • Its operation and maintenance will be carried out by Kuantum Enerji for 15 years.
SİDAŞ Zara Solar Power Plants source image
SİDAŞ Zara Solar Power Plants aerial source image
Company Experiences Finished

SİDAŞ Zara Solar Power Plants

SİVAS / TURKEY

PROJECT NAME
SİDAŞ Zara Solar Power Plants
PLACE
SİVAS / TURKEY
EMPLOYER
EPC
START OF DATE
2026
FINISH OF DATE
2026

SCOPE OF WORKS

  • Annual Production (kWh/year): 1,835,000 × 1
  • Annual Radiation (kWh/m²): 1,835
  • Installed Capacity (kWp): 1,004.4
  • The self-consumption solar power plant of SİDAŞ, a company belonging to Sivas Municipality, has been installed.
MARY 3 Combine Cycle Power Plant Project source image
Founder’s Experiences

MARY – 3 COMBINE CYCLE POWER PLANT PROJECT – 1.600 MW

MARY / TURKMENISTAN

PROJECT NAME
MARY – 3 COMBINE CYCLE POWER PLANT PROJECT – 1.600 MW
PLACE
MARY / TURKMENISTAN
EMPLOYER
TURKMEN ENERGO CORPARATION
START OF DATE
2015
FINISH OF DATE
2017

SCOPE OF WORKS

  • 4 X GENERAL ELECTRIC FRAME 9FA GAS TURBINES, 2 STEAM TURBINES, 4 X HRSG, SUBSTATION (110 kV + 220 kV + 500 kV), BOP, WATER TREATMENTS, 100 km Natural Gas Pipe Line, 2 X RMS
WATAN Simple Cycle Power Plant Project source image
Founder’s Experiences

WATAN SIMPLE CYCLE POWER PLANT PROJECT – 264 MW

WATAN / TURKMENISTAN

PROJECT NAME
WATAN SIMPLE CYCLE POWER PLANT PROJECT – 264 MW
PLACE
WATAN / TURKMENISTAN
EMPLOYER
TURKMEN ENERGO CORPARATION
START OF DATE
2015
FINISH OF DATE
2016

SCOPE OF WORKS

  • 2 X GENERAL ELECTRIC FRAME 9E GAS TURBINES SUBSTATION (110 kV + 220 kV), WATER TRAITMENT, BOP
NAINAWA Simple Cycle Power Plant Project source image
Founder’s Experiences

NAINAWA SIMPLE CYCLE POWER PLANT PROJECT – 750 MW

MOSUL / IRAQ

PROJECT NAME
NAINAWA SIMPLE CYCLE POWER PLANT PROJECT – 750 MW
PLACE
MOSUL / IRAQ
EMPLOYER
IRAQ MOE CORPARATION
START OF DATE
2011
FINISH OF DATE
2013

SCOPE OF WORKS

  • 6 X GENERAL ELECTRIC FRAME 9E GAS TURBINES, GIS (132 kV + 400 kV), CRUDE OIL TRAITMENT, WATER TRAITMENT, TANKS, BOP
AL KHAIRAT Simple Cycle Power Plant Project source image
Founder’s Experiences

AL – KHAIRAT SIMPLE CYCLE POWER PLANT PROJECT – 1.250 MW

KARBALA / IRAQ

PROJECT NAME
AL – KHAIRAT SIMPLE CYCLE POWER PLANT PROJECT – 1.250 MW
PLACE
KARBALA / IRAQ
EMPLOYER
IRAQ MOE CORPARATION
START OF DATE
2011
FINISH OF DATE
2013

SCOPE OF WORKS

  • 10 X GENERAL ELECTRIC FRAME 9E GAS TURBINES, GIS (132 kV + 400 kV), CRUDE OIL TRAITMENT, WATER TRAITMENT, TANKS, BOP
DASHOGUZ Simple Cycle Power Plant Project source image
Founder’s Experiences

DASHOGUZ SIMPLE CYCLE POWER PLANT PROJECT – 256 MW

DASHOGUZ / TURKMENISTAN

PROJECT NAME
DASHOGUZ SIMPLE CYCLE POWER PLANT PROJECT – 256 MW
PLACE
DASHOGUZ / TURKMENISTAN
EMPLOYER
TURKMEN ENERGO CORPARATION
START OF DATE
2006
FINISH OF DATE
2007

SCOPE OF WORKS

  • 2 X GENERAL ELECTRIC FRAME 9E GAS TURBINES SUBSTATION (110 kV), BOP
BALKANABAT Simple Cycle Power Plant Project source image
Founder’s Experiences

BALKANABAT SIMPLE CYCLE POWER PLANT PROJECT – 256 MW

BALKANABAT / TURKMENISTAN

PROJECT NAME
BALKANABAT SIMPLE CYCLE POWER PLANT PROJECT – 256 MW
PLACE
BALKANABAT / TURKMENISTAN
EMPLOYER
TURKMEN ENERGO CORPARATION
START OF DATE
2009
FINISH OF DATE
2010

SCOPE OF WORKS

  • 2 X GENERAL ELECTRIC FRAME 9E GAS TURBINES SUBSTATION (110 kV + 220 kV), BOP
ALMS Simple Cycle Power Plants Project source image
Founder’s Experiences

ALMS SIMPLE CYCLE POWER PLANTS PROJECT – 450 MW

AHAL – 3 (150 MW), LEBAP (150 MW), MARY – 2 (150 MW), / TURKMENISTAN

PROJECT NAME
ALMS SIMPLE CYCLE POWER PLANTS PROJECT – 450 MW
PLACE
AHAL – 3 (150 MW), LEBAP (150 MW), MARY – 2 (150 MW), / TURKMENISTAN
EMPLOYER
TURKMEN ENERGO CORPARATION
START OF DATE
2013
FINISH OF DATE
2014

SCOPE OF WORKS

  • 3 X 3 GENERAL ELECTRIC LM6000 GAS TURBINES SUBSTATION (110 kV + 220 kV), BOP, WATER TREATMENTS
DERWEZE Simple Cycle Power Plant Project source image
Founder’s Experiences

DERWEZE SIMPLE CYCLE POWER PLANT PROJECT – 512 MW

DERWEZE / TURKMENISTAN

PROJECT NAME
DERWEZE SIMPLE CYCLE POWER PLANT PROJECT – 512 MW
PLACE
DERWEZE / TURKMENISTAN
EMPLOYER
TURKMEN ENERGO CORPARATION
START OF DATE
2014
FINISH OF DATE
2015

SCOPE OF WORKS

  • 4 X GENERAL ELECTRIC FRAME 9E GAS TURBINES SUBSTATION (110 kV + 220 kV), WATER TRAITMENT, BOP